Skip to main content

Types of Milestones in Planera

There are 3 types of milestones in Planera

Updated today

Types of Milestone Constraints:

  1. Start Milestone - One must be added to a project and start date must be set here before project can be scheduled

    • Start Milestones in a project imported from P6 will convert to Start of Next Day (SOND) relative to its predecessor in Planera

    • Start Milestones in a project imported from P6 with As Late As Possible (ALAP) constraint will be converted to Start of Next Day (SOND) relative to its predecessor in Planera

  2. Interim Milestone - You can add as many as you like, and this is to track important Interim deadlines

    • Constraints available on Interim Milestone:

      • None - Next day

      • None - End of day (EOD)

      • Start On

      • Finish On

      • Start On or After

      • Finish On or After

      • Finish On or Before

      • As Late As Possible - Next day

      • As Late as Possible - EOD

  3. Finish Milestone - You can add only one to the project.

    • Constraints available on Finish Milestone:

      • Finish On

      • Finish On or After

      • Finish On or Before

    • Finish Milestones from project imported from P6 will convert to End of Day (EOD) relative to its predecessor in Planera

    • Finish Milestones in a project imported from P6 with As Late As Possible (ALAP) constraint will be converted to End of Day (EOD) relative to its predecessor in Planera

Did this answer your question?