Types of Milestone Constraints:
Start Milestone - One must be added to a project and start date must be set here before project can be scheduled
Start Milestones in a project imported from P6 will convert to Start of Next Day (SOND) relative to its predecessor in Planera
Start Milestones in a project imported from P6 with As Late As Possible (ALAP) constraint will be converted to Start of Next Day (SOND) relative to its predecessor in Planera
Interim Milestone - You can add as many as you like, and this is to track important Interim deadlines
Constraints available on Interim Milestone:
None - Next day
None - End of day (EOD)
Start On
Finish On
Start On or After
Finish On or After
Finish On or Before
As Late As Possible - Next day
As Late as Possible - EOD
Finish Milestone - You can add only one to the project.
Constraints available on Finish Milestone:
Finish On
Finish On or After
Finish On or Before
Finish Milestones from project imported from P6 will convert to End of Day (EOD) relative to its predecessor in Planera
Finish Milestones in a project imported from P6 with As Late As Possible (ALAP) constraint will be converted to End of Day (EOD) relative to its predecessor in Planera