How to Track Planned Percent Complete (PPC)

Learn how to activate Planned Percentage Complete and understand the key functions you can perform once it is enabled

Latest Update: 10-2-2026

Planned Percentage Complete (PPC) enables you to monitor your project's progress by comparing planned activities with actual completions, providing a clear overview of project health. You can view this data directly from the Project Dashboard.
​


​Note: By default, Planned Percentage Complete is disabled, which means the progress graph will not be visible on the Dashboard until it is enabled
​

How to Enable Planned Percentage Complete

  1. Open Project Settings from the project dashboard (Option 1) or from the "More" menu while in the Build or Analyze section of a project (Option 2)
    ​


    ​

  2. Navigate to "Planned Percentage Complete" and enable
    ​


    ​Note: When Planned Percentage Complete (PPC) is enabled, use the Planning state to set up your schedule, then switch to the Committed state to update progress.


    Learn how to switch states here
    ​

How Planned Percentage Complete is Calculated

Planned Percentage Complete (PPC) tracks project progress by comparing the number of completed activities to the total planned activities within a specific period.

Visual Indicators:

  • Red: Less than 75% of planned activities are complete

  • Yellow: 75–90% of planned activities are complete

  • Green: Over 90% of planned activities are complete
    ​


​Note: For accurate data, Field Schedules should be in "Committed" state
​
​

Viewing progress by codes

  1. Select a Code from the Drilldown dropdown
    ​


    ​

  2. Once selected the chart will display lines which represent progress for each code over time
    ​


    ​

Viewing Critical Path Progress

  1. Select Critical Path on the Paths dropdown to see your PPC for critical path items only

  2. Select Show Total PPC Reference to see the total PPC next to your colorized critical path

PPC Data From Multiple Versions

  • When more than 1 version exists, PPC data is pulled from the current version and all prior versions in the version chain that have progress updates
    ​

  • If an activity has progress updates in multiple versions, the version that was updated last wins and that data is used to calculate PPC

  • Once an activity has updated status of "in progress" or "completed", committed dates will be locked to ensure that the historical data is not changed every time the project goes back into planning state