How to Switch Between Progress Override and Retained Logic

This article explains how to change the scheduling mode used when progressing activities, so you can control whether logic is recalculated or retained during schedule updates.

Latest Update: 10-2-2026

When working with progressed schedules, Planera allows you to choose how logic behaves after actuals are entered. Switching between Progress Override and Retained Logic ensures your schedule reflects the level of logic preservation you need.

Change the Schedule Progress Mode

  1. Open the project you want to update

    Make sure you are in the Master Schedule where schedule settings are managed.

  2. Go to the More menu and open Schedule Settings

    Click the settings icon in the schedule toolbar to access project-level scheduling options.

  1. Select the desired progress mode

    Under Progress Behavior, choose one of the following:

    • Retained Logic – Original logic is preserved, and remaining work respects existing relationships

    • Progress Override – Logic is recalculated based on progress and the data date

  2. Save your changes

    The selected mode will apply the next time the schedule is progressed or recalculated

Need more information on which Scheduling Mode is right for your project? Read more in this help article.