Types of Milestone Constraints:
- Start Milestone - No constraint but start date must be set here before project can be scheduled 
- Interim Milestone - You can add as many as you like, and this is to track important Interim deadlines. - Constraints available on Interim Milestone: - Start On 
- Finish On 
- Start On or After 
- Finish On or Before 
 
 
- Finish Milestone - You can add one of these to the project. - Constraints available on Finish Milestone: - Finish On 
- Finish On or Before 
 
 
Types of Activity Constraints:
- Constraints available on Activities and Tasks: - Start On 
- As Late as Possible 
 