Skip to main content

Tracking Planned Percentage Complete (PPC)

Learn how to activate Planned Percentage Complete and understand the key functions you can perform once it is enabled

Updated over 2 weeks ago

Planned Percentage Complete (PPC) enables you to monitor your project's progress by comparing planned activities with actual completions, providing a clear overview of project health. You can view this data directly from the Project Dashboard.


Note: By default, Planned Percentage Complete is disabled, which means the progress graph will not be visible on the Dashboard until it is enabled

How to Enable Planned Percentage Complete

  1. Open Project Settings from the project dashboard (Option 1) or from the “More” menu while in the Build or Analyze section of a project (Option 2)


  2. Navigate to “Planned Percentage Complete” and enable


    Note: When Planned Percentage Complete (PPC) is enabled, use the Planning state to set up your schedule, then switch to the Committed state to update progress.


    Learn how to switch states here


How Planned Percentage Complete is Calculated

Planned Percentage Complete (PPC) tracks project progress by comparing the number of completed activities to the total planned activities within a specific period.

Visual Indicators:

  • Red: Less than 75% of planned activities are complete

  • Yellow: 75–90% of planned activities are complete

  • Green: Over 90% of planned activities are complete


Note: For accurate data, project should be in “Committed” state

Viewing progress by codes

  1. Select a Code from the drilldown dropdown


  2. Once selected the chart will display lines which represent progress for each code over time


PPC Data From Multiple Versions

  • When more than 1 version exists, PPC data is pulled from the current version and all prior versions in the version chain that have progress updates

  • If an activity has progress updates in multiple versions, the version that was updated last wins and that data is used to calculate PPC

  • Once an activity has updated status of "in progress" or "completed", committed dates will be locked to ensure that the historical data is not changed every time the project goes back into planning state


Did this answer your question?