Skip to main content
All CollectionsWorking Schedule
Planning and Committed States of Project
Planning and Committed States of Project

How to switch Project state between Planning and Committed

Updated this week

In order to accurately calculate PPC (Planned Percent Complete), system has to determine the committed date of each activity and task.

To facilitate that, project will have 2 states:

Planning State: This is when you can create a schedule and make adjustments
Committed State: This is when you add progress update and PPC is calculated accordingly

How to enable Planning and committed states

By default, the Project State is hidden until PPC (Planned Percentage Complete) is enabled in project settings. Once enabled, the state defaults to Planning.

Use the info icon in the header or the “More” menu to check the current project state.

Planning State

Each new project and version automatically starts in Planning state.
In Planning, you can, add or edit elements, adjust durations, create relationships, etc.

However progress updates are restricted in Planning state. To update progress, switch to Committed state.

Committed State

When a project is moved to Committed state, dates are locked and become the basis to calculate PPC going forward. In Committed state, you can:

  • Update activity progress

  • Track PPC on the dashboard

Changing schedule in committed state

If you wish to make any changes to the schedule when project is in Committed State, the project automatically switches back to Planning, and team members are notified via email.

How to switch project state

  1. Click “Project State” in the more menu


  2. Select “Committed” and save to change project state


Did this answer your question?