Data Transfer Between Master Schedule and Field Schedule

How data flows between the Master Schedule (Master Schedule) and the Field Schedule (Field Schedule)

Updated yesterday

What Data Moves Between Master and Field Schedules in Planera?

This article explains how data flows between the Master Schedule (Master Schedule) and the Field Schedule (Field Schedule) in Planera - both at the time of Field Schedule creation and during ongoing updates. It also covers how data behaves across Field Schedule versions.


From Master Schedule to Field Schedule

When a Field Schedule version is created, it pulls in a snapshot of data from the Master Schedule. After this point, the Field Schedule is independent and no longer receives updates from the Master Schedule (with the exception of the critical path).

This design ensures that field teams have a stable baseline to plan against, without disruptions from ongoing changes in the master plan.

What flows from Master Schedule to Field Schedule:

  • Activities: All planned and actualized activities that overlap with the Field Schedule date range

  • Calendar, Resources, and Codes: Carried over from Master Schedule

  • Critical Path: Updated dynamically from Master Schedule, even after Field Schedule creation

  • Data Date: Initially set to "From Date" during creation; should be updated as the schedule is used

  • User Access & Permissions:

    • Master Schedule users are not automatically added to Field Schedule

    • Permissions can differ between Master Schedule and Field Schedule

    • Users can be invited directly to Field Schedule without needing Master Schedule access

What does not flow from Master Schedule to Field Schedule:

  • Comments from Master Schedule

  • Ongoing updates to Master Schedule activities, logic, or data (after Field Schedule creation)


From Field Schedule to Master Schedule

Once a Field Schedule is created, certain updates can flow back to the Master Schedule—but only if the Field Schedule is scheduled (i.e., not stale).

What flows from Field Schedule to Master Schedule:

  • Progress updates: Actual Start, Actual Finish, Expected Finish

What does not flow to Master Schedule:

  • Tasks created in Field Schedule

  • New or edited activity groups

  • Logic, codes, and resource changes

  • Calendar or resource reassignments

  • Percent Plan Complete (PPC)

  • Field Schedule Variance Codes

Note: Field Schedule details are often more granular than what’s needed in the Master Schedule. This intentional separation helps keep the master schedule clean and focused.


Between Field Schedule Versions

When a new Field Schedule version is created, some data is carried forward and some is updated based on the latest Master Schedule.

What is carried forward from the previous Field Schedule version:

  • Progress updates

  • Task details inside an Activity

  • Activities and tasks that are not complete as of the new Field Schedule "From Date"

What is brought in fresh from Master Schedule:

  • New activities and milestones, along with their relationships

  • Updated critical path (re-marked based on latest Master Schedule)

What is not updated in Field Schedule even if changed in Master Schedule:

  • Logic (e.g., if relationships between activities change in Master Schedule)

  • Codes or resource assignments

  • Any other edits to existing Field Schedule activities

Completed activities are archived and removed from the current Field Schedule version but remain accessible in the previous one.


Summary Table

Data Type / Action

MS → FS (At FS creation)

FS → MS (Progress update)

New FS Versions

Notes / Rationale

Activities (planned & actualized)

✅ Pulled in if within date range

🚫

✅ Retained or archived

Snapshot-based transfer to enable stable FS planning

New Activities / Groups

✅ New MS items pulled into new FS version

🚫

✅ Added in new FS version only

New FS version required to reflect MS changes

Activity Group Changes

✅ If from MS at creation

🚫

🚫

FS does not sync ongoing MS changes post-creation

Progress Updates (Actual/Expected Finish)

🚫

✅ If FS is scheduled (not stale)

✅ Carried forward

Enables real-time field progress to be visible in MS

Logic Changes

🚫

🚫

🚫

FS keeps original logic snapshot; avoids MS overwriting FS planning

Calendar / Resources / Codes

✅ Included at time of FS creation

🚫

🚫

No continuous sync; keeps FS localized and stable

Critical Path

✅ Preserved from latest MS

🚫

✅Pulled in for each new FS version

Only MS-to-FS data that stays current without new FS version

Comments

🚫

🚫

🚫

Comments are local to MS or FS only

Tasks

🚫

🚫

✅ Carried forward if incomplete

FS tasks are more detailed and stay within FS

Variance Codes

🚫

🚫

🚫

Stay within FS for field-specific tracking

PPC (Percent Plan Complete)

FS level calculation

MS level calculation

🚫

Localized to FS; not rolled up

FS Task Assignments

🚫

✅ Retained

Do not inherit resource/code assignments from MS parent

Resource Rollups

🚫

FS-assigned resources do not roll up to enterprise dashboards

Completed Activities

✅ Archived from current FS

Visible in previous FS versions only

User Access / Permissions

Manual

Manual

Access & permissions differ between MS and FS

Data Date

Set as "From Date". Should be updated as needed

Should be updated manually

Used for filtering and version control