Field Schedule provides a focused view of your project, enabling you to break activities into tasks with durations and logical connections within each activity. You can create detailed short duration plans for your team. Field Schedules create a slice from an Existing Master Schedule.
How to Create a Slice from an Existing Master Schedule
Pull a slice from a selected master schedule by choosing the from date and the number of weeks.
Click “New Project” on the “All Projects” page
On the Create a New Project page, select “Field Schedule”
After selecting Filed Schedule, you’ll be taken to the next section. Select a Master Schedule from the dropdown then a version
Set the Field Schedule start date and lookahead duration in weeks, then click “Next”
Note: The number of weeks you select when creating a Field Schedule becomes the minimum duration for all future field schedule versions.
Select resources and codes to import
Enter a name, set a default calendar and Create Project