Latest Update: 10-14-2026
When you ask Manny to co-edit your schedule, it works within a defined set of capabilities. This article covers exactly what Manny can and can't change. For step-by-step instructions on how to apply changes or run a scenario, see Co-Edit Schedules With Manny.
What Manny Can Change
Manny can make the following types of changes to your schedule:
Add, rename, or delete activities, milestones, and groups. Manny can create new schedule items, update their names, durations, and dates, and delete them.
Add or remove logic ties. Manny can create Finish-to-Start (FS), Finish-to-Finish (FF), and Start-to-Start (SS) relationships between activities, update their lag and lag type, and delete them.
Reorganize the schedule hierarchy. Manny can add activities into a group or remove them from one.
Add or remove codes and resources. Manny can help assign codes and resource load your schedule based on your library and existing codes.
Change calendars. Manny can update some or all of the elements in your schedule to a different calendar from your libraray.
Read, update and create notes. Manny can read, update or create notes in your project.
What Manny Cannot Change
The following actions are not supported and must be done manually in Planera:
Progress and status. Manny cannot update progress status, percent complete, or any other progress fields on an activity. Use the progress update workflow in Planera to enter these manually.
Activity codes. Manny cannot create code types or add new code values.
Create resources. Manny cannot create new labor or equipment resources.
Calendars. Manny cannot create or edit calendars.
Comments. Manny can read comments attached to activities, but cannot add or edit them.
Colors. Manny cannot assign or update colors for schedule elements or codes.
Rules to Know
Keep these in mind when asking Manny to make changes:
Relationship type cannot be changed directly. To change an existing logic tie from FS to FF, for example, Manny must delete the existing tie and create a new one. Type is fixed once a relationship is created.
Start-to-Finish (SF) relationships are not supported. Manny cannot create SF logic ties.
Logic ties cannot be added to text or image elements.
Each schedule can have only one start milestone and one finish milestone. Manny cannot add a second one if one already exists.
Start and finish milestones belong in Master schedules. Manny cannot create start or finish milestones in a Field (Working) schedule, except when restoring a previously deleted one.
Task-type activities belong in Field schedules. Manny cannot add tasks to a Master schedule.
Duration ranges can only be set on activities that haven't started. Manny cannot update a duration range on an activity that is in progress or complete.
Frequently Asked Questions
Can Manny change a logic tie from FS to FF?
Not directly. Relationship type is fixed once created. Ask Manny to delete the existing tie and create a new one with the type you want.
Why won't Manny update the status or progress on my activities?
Progress updates are intentionally excluded from Manny's co-editing capabilities. Status, percent complete, and other progress fields must be entered manually through the progress update workflow in Planera.
Can Manny assign a calendar to an activity?
No. Calendar assignments must be done manually in Planera.
Can Manny assign codes to activities?
Yes. Manny can assign codes to activities but code types and values must be managed manually so build out your codes first and ask Manny to assign them for you.
Can Manny assign resources to activities?
Yes. Labor and equipment assignments that exist in your company library can be assigned through Manny's co-editing capabilities. Creating new resources must be done manually.
Can I add more than one start or finish milestone using Manny?
No. Each schedule supports only one start milestone and one finish milestone. Manny cannot add a second one.
What types of logic ties can Manny create?
Manny can create Finish-to-Start (FS), Finish-to-Finish (FF), and Start-to-Start (SS) logic ties. Start-to-Finish (SF) is not supported.