Skip to main content

Inspecting the Path of an Activity or Milestone

How to trace logic path of an activity or milestone.

Updated over 3 weeks ago

Latest Update: 3-12-2026

Viewing an activity or milestone’s logic path can be useful for a clear, uncluttered view of its related elements. You can inspect the path of any activity or milestone in from the Canvas, Table, Gantt or Watchlist view to better understand your schedule.

Inspect the Path of an Activity

Inspecting a path in canvas shows opens a full screen view of the logic path of an activity or milestone. Three levels of predecessors and successors for the selected element will be shown by default.

Each expansion reveals three additional levels.

Driving vs. Non-Driving Relationships

The driving path of all visible activities will be shown via a thickened edge. Refer to the legend in the bottom left as needed to remember the nuances here. When an activity has multiple predecessors, the driving relationship is represented with a bold line and all other non-driving relationships are standard line thickness.

Inspect Path From Canvas

  1. Right click on an activity or milestone and select Inspect Path - Canvas

  2. To stop inspecting, navigate to the upper left hand side of your screen and choose Back to Project

Inspect Path From Table

Right click on an activity or milestone and select Inspect Path - Canvas

Inspect Path From Watchlist

Hover over an activity or milestone, click on the 3 dots to reveal the menu and select Inspect Path - Canvas

Inspect Path From Gantt

Inspecting a path in Gantt will filter for the predecessors and successors of the selected activity or milestone.

  1. Right click on an activity or milestone and choose Inspect Path - Gantt

  2. You will get a filtered view of the predecessors and successors related to that activity or milestone

  3. To stop inspecting, navigate to the upper right hand side of your screen in Gantt, and choose Stop Inspecting

Filtering While Inspecting an Element's Path

You can apply, update or turn off a filter to the inspected path the same way you do in canvas

Critical Path

You can toggle on or off the critical path and alternate float paths while inspecting the path of an element

Center Inspected Element

Use the Center Element button to return to the inspected element

Canvas Display Options

Use the settings wheel in the lower right to toggle activity dates and progress bars on/off and choose whether to display Total Float, Free Float or Remaining Duration below each element

Did this answer your question?