Adding a Milestone

What are Milestones and how to add one to the project

There are three types of Milestones in Planera:

  1. Start Milestone - One is required, and this is where you set the start date of the project

    • Constraints available on Start Milestones:

      • Start Milestones in a project imported from P6 will convert to Start of Next Day (SOND) relative to its predecessor in Planera

      • Start Milestones in a project imported from P6 with As Late As Possible (ALAP) constraint will be converted to Start of Next Day (SOND) relative to its predecessor in Planera
        ​


    ​

  2. Interim Milestone - You can add as many as you like, and this is to track important Interim deadlines.

    • Constraints available on Interim Milestone:

      • None - Next day (this is the default)

      • None - End of day (EOD)

      • Start On

      • Finish On

      • Start On or After

      • Finish On or After

      • Finish On or Before

      • As Late As Possible - Next day

      • As Late as Possible - EOD

  3. Finish Milestone - You can add one of these to the project.

    • Constraints available on Finish Milestone:

      • Finish On

      • Finish On or After

      • Finish On or Before

    • Finish Milestones from project imported from P6 will convert to End of Day (EOD) relative to its predecessor in Planera

    • Finish Milestones in a project imported from P6 with As Late As Possible (ALAP) constraint will be converted to End of Day (EOD) relative to its predecessor in Planera

How to add Milestones to the project

  1. Using Left Toolbar
    ​

    1. Hover over the left Toolbar and select the Milestones
      ​


      ​

    2. Select the type of Milestone and click on the desired spot on the canvas to add it. A Milestone will be created in that spot.
      ​

  2. Right click on the canvas and select “Interim Milestone”. A Milestone will be created in that spot.
    ​