Set the Data Date in Two Ways
Through the (i) Icon
Click on (i) icon in the top center of the screen to the right of the project name
Click the edit icon next to the Data Date
Enter the new data date
Through the Progress Update Panel
Go to the More menu and select Progress Updates
Note: You can open the Progress Updates panel in any view (Canvas, Gantt or Table)
Select Change Data Date to update the Data Date
Note: You may need to expand the top section of the Progress Update List by clicking on the ^ next to the current Data Date.
When you run your schedule, the Planned Start of any activities missing a predecessor or whose predecessor is complete will move to the data date. Refer to this article to learn more: Move Now vs Move Later