Latest Update: 10-2-2026
View the Quality Score in a resizable side panel that will stay open as you navigate between the Canvas, Table, and Gantt views. This lets you refer to the quality score criteria while inspecting activities that affect your score at the same time.
How to Access the Schedule Quality Report
You can access the Quality Report two ways:
2. Through the More menu select Schedule Quality Check
Understanding your Quality Score
The categories at the top of the Schedule Quality Report in the Network Integrity section measure the network structure and relationships of your schedule. These values affect your Quality Score. You can learn more about each category by hovering over the info icon.
Red values in the report highlight items that exceed acceptable thresholds and require attention. These indicators do not necessarily mean your schedule is broken but serve as a prompt to review and address potential issues. To understand why an item is flagged, click the magnifying glass icon next to the value for that category. This will apply a filter to your project so you can walk through each offending scenario and correct as needed.
The 6 categories at the bottom of the side panel in the Project Execution section measure project performance and do not impact the Quality Score.
Improving Your Quality Score
Click on the magnifying glass in the value column to investigate offending elements in your schedule by applying filters.
Use the arrows to review the element affecting your score.
To switch to another quality category, click the magnifying glass next to a new category and click Continue to update the filters and inspect the filtered elements to make updates
To close the quality check and remove all filters, click Stop Inspecting next to the category you are inspecting or toggle the filter off
Note: Prioritize resolving "Missing logic" and "Missing duration" items first, as these have the most significant impact on your schedule's quality.
For more information on customizing the quality score for your organization, read this help article.
Frequently Asked Questions
How do I access the Schedule Quality Report?
Two ways: after running the schedule, click View Quality Report in the popup, or go to the More menu inside your project and select Schedule Quality Check.
What is the difference between the Network Integrity and Project Execution sections?
The 8 Network Integrity categories measure your schedule's structure and logic, and they directly affect your quality score. The 6 Project Execution categories measure project performance but do not impact your score.
How do I find out which activities are hurting my quality score?
Click the magnifying glass next to any Network Integrity category in the quality report panel. Planera applies a filter so you can see only the activities affecting that category. Use the arrows to step through them one at a time.
Can I inspect more than one quality category at the same time?
Not simultaneously. To switch categories, click the magnifying glass next to a new category and click Continue. Planera replaces the previous filter with the new one.
How do I close the quality check and remove the filters?
Click Stop next to the category you are inspecting, or toggle the filter off. This closes the quality check and clears all filters from your schedule view.