Bulk Actions: Add Content to Multiple Activities at Once
Bulk Actions allow you to update values such as Calendar, Labor, and Codes across multiple selected cells in the same column or across an entire row. You can either enter new values or copy and paste existing data.
By selecting a Row at a time
How to perform bulk actions by selecting multiple table rows
Hover over an activity to reveal a checkbox in place of the S/N. column, then check the boxes for the activities you want to update.
Tip: To select all activities, click on the S/N box at the top
Once selected, a Bulk action strip will appear at the bottom of the screen
From the strip, choose one of the following bulk actions:
Find and replace
Calendar
Labor
Equipment
Codes
Select the desired action and apply the changes to all the selected activities
To cancel any bulk changes, select 'Cancel.' This action will prompt a modal where you can confirm the cancellation.
Note: You can select a group, which automatically selects all its child elements.