How to Use the Project Dashboard

Project analytics, progress S-curve, Important dates variance, and more

Latest Update 10-2-2026


The project dashboard offers a real-time overview of key performance indicators, enabling you to monitor and analyze the project progress and performance of the current version in comparison with the baseline.
​
​Note: The Dashboard's version comparison (current vs. baseline) differs from the project version comparison, and these functionalities work independently.

How to access Dashboard: Click the Dashboard icon from the left toolbar


​

Note: Data displayed on the page is not real-time updated. Click "Refresh" for the latest information.
​

How to Set Baseline from the Dashboard

Baseline can be set in 4 ways from the baseline dropdown.

  1. Select Existing Baseline
    ​

    • Click the option labeled 'Baseline' from the dropdown.
      ​


      ​

  2. Assigning baseline when none has been assigned previously
    ​

    • Click the option labeled 'Assign Baseline' from the dropdown menu.
      ​


      ​

    • Click on any schedule version, except the current one, to set it as the baseline.
      ​


      ​Note: Learn more about setting baseline here.
      ​
      ​

  3. Select 'Previous'
    ​

    • Click the option labeled 'Previous' from the dropdown menu.
      ​


      ​Note: This sets the version created before the current version as baseline
      ​
      ​

  4. Select 'Other Versions'
    ​

    • From the dropdown, click on 'Other Versions' to access the version canvas, which displays all schedule versions.
      ​


      ​

    • Click on a schedule version to set as baseline.
      ​


      ​

Using Progress S Curve

  • Show baseline on Progress S Curve graph: Click on the "Early Start" and "Late Start" checkboxes to respectively display the baseline curve on the graph.
    ​


    ​

  • Display data over various time periods: Choose between Day, Week, Month, or Year to refine the chart and showcase progress data accordingly.
    ​

    ​
    ​

Adding To Watchlist

  1. Click on 'Add to Watchlist' to open 'Watch an Activity/Milestone' modal
    ​


    ​

  2. Hover over any Activity or Milestone and click on 'Watch' to add to watchlist.
    ​


    ​

  3. Elements added to the watchlist in the current version will appear in the table.
    ​


    ​Note: Learn more about watchlist here.
    ​

    Download Project Dashboard​

    You can download the dashboard by selecting the Download PDF button at the top right of the Project Dashboard
    ​


Note: This will download all charts and graphs as a multi-page PDF and tables will be included as a multi-tab excel file.​


​