Importing Projects From P6

How to Import projects from P6 and export projects to P6 

Latest Update: 7-17-2026

For specific information on what data is preserved during P6 import and export, please reach out to our Planera Customer Success team through the support chat in the bottom right corner of any Planera screen (CTRL + H).

Important Points to Note Before Importing a P6 project into Planera

  1. What's Imported: All logic, durations, start/finish milestones (with supported constraints), progress updates, activity codes, UDFs, labor, equipment resources (including cost loading) and WBS order.
    ​

  2. Conversion: LOE activities convert to Timespan resources and hourly durations convert to days.
    ​

  3. For a smooth importing experience make sure:

    1. All durations are whole and not fractional

    2. Calendars are setup with consistent work hours for any exceptions.
      ​

  4. If Import Fails: A log file will be generated, and Planera Customer Success will assist with the issue.
    ​
    ​

How to Import P6 project into Planera

  1. From within P6 go to ‘File’ and click ‘Export’
    ​


    ​

  2. Choose ‘Primavera P6 - (XML)’ and complete the export
    ​


    ​Important Points to Note:
    ​

    • All logic, durations, progress updates, activity codes, UDF’s and WBS order will be exported exactly like an XER file
      ​

    • XML file is version-independent, so no modifications are needed for importing

    • Planera supports XER imports for P6 v20 and newer
      ​
      ​

  3. Open Planera, click the upload icon on the homepage and upload your P6 XML file
    ​


    ​Note: All logic, durations, start/finish milestones (with supported constraints), activity codes, UDF’s, WBS order, progress updates, and resource cost loading data will be imported.
    ​

    • If issues are found, resolve them. Learn more
      ​
      ​

  4. The uploaded file will appear at the top of the workspace. Once opened, a visual AI will be applied to generate the visual layout of the project. Select your preferred layout, and click ‘Apply’
    ​


    ​Note: Learn how to export a Planera project into P6 (XML) here

Note: Primavera P6 has hundreds of settings and versions. If importing the project to P6 does not work the first time, please contact us, and we will resolve the issue promptly. Once resolved, you can use this functionality without any further assistance from us.


​