Identify Driving Relationships

Quickly identify which relationships are driving and which are on the critical path

Updated today

Latest Update 4-13-2026

You can click on any activity, task, or milestone in Canvas or Gantt to instantly see which connected relationships are driving, and which are both driving and critical. This makes it easier to quickly understand schedule impact.

View Driving & Critical Relationships 3 Ways

Canvas (Option 1)

In Canvas view, click on any activity, task, or milestone

Review the highlighted relationships connected to the selected item:

  • Driving relationships will be visually identified

  • Relationships that are both driving and critical will also be indicated

  • Non-driving relationships will remain unhighlighted

Canvas (Option 2)

In Canvas, right-click any activity and select Inspect Path - Canvas

Review the connections to the activity you are inspecting using the toolbar at the top:

Toggle between:

  • All - Show driving and non-driving connected activities

  • Driving Only - Show only connected activities on the driving path

  • Backward - Show only connected predecessors

  • Both - Show connected predecessors & successors

  • Forward - Show only connected successors

Gantt

In Gantt, right-click any activity and select Inspect Path - Gantt

Review the connections to the activity you are inspecting using the toolbar at the top:

Toggle between:

  • All - Show driving and non-driving connected activities

  • Driving Only - Show only connected activities on the driving path

  • Backward - Show only connected predecessors

  • Both - Show connected predecessors & successors

  • Forward - Show only connected successors

  • Show WBS - Toggle the WBS (Group) structure and show only activities

What This Means

  • Driving relationships directly impact the successor’s start or finish date

  • Driving + critical relationships both drive the successor and fall along the project’s critical path

  • This interaction allows you to quickly assess schedule risk and impact without leaving Canvas or Gantt