Skip to main content

How to Connect Activities and Elements in Planera's Canvas

How to connect Activities in the same group or a different group

Latest Update: 9-29-2026

This article explains all the ways you can create new relationships (dependencies) between activities in Planera from the Canvas, the Gantt Chart, the Table.

For instructions on editing relationship types or lag, see: Defining Relationships and Lags

What Is a Relationship?

A relationship (also called a dependency) connects two activities to define their sequencing. When you create a new relationship, Planera uses a Finish-to-Start (FS) link with 0 lag by default. You can adjust the type and lag after the relationship is created. All relationship arrows that do not have an identifier are FS with 0 lag.

Creating Relationships on the Canvas

The Canvas is the most visual way to create relationships. You can draw connectors directly between activities.

How to Connect Activities in the Same Group​

  1. Hover over an activity. A blue connection point appears on the left and right edges

    Note: The same action starting from the left of an Activity box will create a predecessor.

    1. Hover on the left 30% to create a predecessor relationship

    2. Hover on the right 70% to create a successor relationship

  2. Click and drag the blue point toward another activity

  3. Release on the target activity creates a new FS relationship

​

How to Connect Activities in a Different Group

  1. Start a connection as above, but instead of ending it on an activity, release your cursor on an empty space on the Canvas


    ​

  2. Click on Connect to Existing
    ​


    ​

  3. Search for the activities you want to connect, select them, update the relationship type as needed on the right side of the element and click Add
    ​

    ​Note: Activities in the same group can also be connected this way. As you type, the Activity Chooser scrolls to the first matching activity so you can see the hit without scrolling the list yourself. If your search returns no results, the window shows an empty list.

How to Narrow the Activity List by Group Level

  1. In the Activity Chooser, click the three-dot menu next to a group

  2. Choose Show Groups to Level and pick the level you want

This works the same way as Show Groups to Level in the Project Navigator, so a schedule with deep group nesting can be collapsed to just the levels you care about before you pick an activity.

How to Switch the Direction of a Relationship

  1. In canvas, right-click on the relationship line you want to modify

  2. From the menu, choose Switch Direction

    1. Switching direction converts the predecessor activity to the successor and vice versa. This is a shortcut for reversing the sequence of two connected activities without deleting and re-creating the relationship.

Note: If switching the direction would create a circular relationship, the Switch Direction option will be grayed out with the tooltip: "Circular connections are not allowed."

Modifying Relationships in the Gantt and Table

Relationships in Table:

  1. Right-click on an activity and choose Show Relationships to see and edit its relationships

  2. This will open the Relationship Window where you can view, add, edit, and delete relationships

    Note: This relationship panel can be moved and resized as needed.

  3. Choose Add Predecessor or Add Successor to create a new relationship. Search for the activity or choose from the dropdown, then click Add

  4. Click the 3 stacked dots next to a relationship and then click Delete Connection

Relationships in Gantt 3 ways:

  1. Right-click on an activity and choose "Show Relationships" to see and edit its relationships

  2. This will Open the Relationship window where you can view, add, edit relationships

    Note: This relationship panel can be moved and resized as needed.

  3. Choose "Add Predecessor" or "Add Successor" to create a new relationship. Search for the activity or choose from the dropdown, then click "Add"

    Note: In the Gantt chart, you can select an activity and click the Relationship icon at the bottom right to open the Relationship window.

  4. You can also click and drag from the left or right of activity bars to create relationships.

  5. Right-click on an activity to Add New Activity or Add New Milestone.

Note: This will open up a canvas view zoomed into the selected element where you can place new activities, milestones and groups. When you are done adding in your fragnet, click Save and Close in the upper right-hand corner.

Note: Learn more about adding relationships in canvas here.

Frequently Asked Questions

How do I reverse a relationship between two activities on the Canvas?
Right-click the relationship line connecting the two activities and choose Switch Direction from the context menu. This flips which activity is the predecessor and which is the successor without deleting and re-creating the connection.

Why is Switch Direction grayed out on some relationships?
Switch Direction is disabled when reversing the relationship would create a circular dependency, meaning Activity A would end up depending on itself through a chain of connections. Hover over the grayed-out option to see the tooltip: "Circular connections are not allowed."

Can I switch the direction of a relationship from the Gantt or Table view?
No. Switch Direction is only available on the Canvas by right-clicking a relationship line. In the Gantt and Table views, you can edit relationships through the Relationship window, but you would need to delete the existing connection and add a new one to reverse direction.

Does switching relationship direction change the relationship type (FS, SS, FF) or lag?
No. Only the direction changes. The relationship type and any lag values are preserved exactly as they were.

What is the difference between a predecessor and a successor?
A predecessor is the activity that must occur before another can start (or finish, depending on the relationship type). A successor is the activity that depends on the predecessor. For example, if Activity A is a predecessor to Activity B with an FS relationship, B cannot start until A finishes.

Did this answer your question?