Latest Update 3-11-2026
You can click on any activity, task, or milestone in Canvas to instantly see which connected relationships are driving — and which are both driving and critical. This makes it easier to understand schedule impact at a glance without toggling between views.
View Driving & Critical Relationships
Navigate to the Canvas view and click on any activity, task, or milestone.
Review the highlighted relationships connected to the selected item:
Driving relationships will be visually identified.
Relationships that are both driving and critical will also be indicated.
Non-driving relationships will remain unhighlighted.
What This Means
Driving relationships directly impact the successor’s start or finish date.
Driving + critical relationships both drive the successor and fall along the project’s critical path.
This interaction allows you to quickly assess schedule risk and impact without leaving Canvas.