How to Troubleshoot Project Import Issues

How to handle issues found in a project while importing a project

Latest Update: 10-2-2026

While importing a project, issues may arise that need to be corrected for a successful import. Learn more about importing a project here

  1. Click the upload icon on the homepage and upload your P6 XML file
    ​


    ​

  2. Click Import
    ​


    ​

  3. Issues found require corrective action. Select an action (Ex- Round Up) and click the right arrow to proceed until all issues are resolved
    ​


    ​Note: If Import Fails a log file will be generated, and Planera Customer Success will assist with the issue
    ​