Bring in a baseline or an earlier version of a schedule from P6 to an ongoing Planera project.
Note: This feature is only available for projects originally imported into Planera and does not apply to projects created directly within Planera.
How to Import a Previous or Baseline Version
Navigate to the Versions of a project that has been imported into Planera.
Click on 'Import Baseline Version' to import a baseline or 'Import Previous Version' to import a previous version
Upload a P6 XML or P6 XER file
If no issues are found, the imported version will appear with an 'Imported' tag
Learn more about Importing a project here