Procore has two scheduling tools, be sure to follow the steps for the correct version your team is using.
Publish to Procore Schedule (Legacy)
Make sure that the Planera app is installed in Procore
Provide project-level permission for the target project to Planera embedded app
Open that target project in Procore
Launch Planera Embed App
Navigate to the right project in the embedded Planera app. Go to the "More" menu, and select "Export Project to Procore"
Once exported, navigate to the Schedule (Legacy) tool in Procore to view your schedule
Publish to Procore Scheduling (New)
Make sure that the Planera app is installed in Procore
Provide project-level permission for the target project to Planera embedded app
Navigate to your project in Procore, then from the Project Tools dropdown choose Procore's Scheduling tool (New)
For projects maintained in Planera, choose option 1 for this initial import.
Drop your file into the import window
Note: You only need to import your project once to be able to push future versions of your schedule to Procore through the embedded Planera App.
Pushing Updates to the New Procore Scheduling Tool
Once you've imported an initial version of your schedule, follow steps 1-5 above from the Legacy tool to push updates of your schedule to your project in Procore. On the last step, choose Procore Scheduling (New) and your Procore Project name from the dropdown and click Export.