Skip to main content
All CollectionsGeneral
WBS/Group Duration Based on Different Calendars
WBS/Group Duration Based on Different Calendars

How to change group duration display between 7-day calendar and the project default calendar

Updated over 7 months ago

Group duration in Planera refers to the total time for a set of activities that have been grouped together. You can view group duration based on:

  1. Calendar Days (7 days a week)

  2. Project Default Calendar of the project

By default “Calendar Days (7 Days a week)” is selected. It can be adjusted within a project from the Canvas, Table or Gantt views.


How to change Group Duration Calendar from the Canvas

  1. Expand a group


  2. Navigate to the right section of the group header and hover over the "Duration" field. A tooltip displaying the applied calendar will appear. Click on "Change" to modify the calendar.


  3. Select the options you want and click “Save


How to change Group Duration Calendar from the Table

  1. Hover over any group in the duration column.


    Note: If you can't find the duration column, add it via the “ADD” button near the last column, the 3-dot menu in a column header, or the dropdown next to the tabs.


  2. Select the options you want and click “Save


How to change Group Duration Calendar from the Gantt

  1. Hovering over any group in the duration column.

    Note: If you can't find the duration column, add it via the “Edit Columns” button above the column headings.

  2. Select the options you want and click “Save

Learn more about creating custom calendars here

Did this answer your question?