Skip to main content

Understand Your Project Performance Dashboard

Explanation of fields and indicators shown on the Project Performance Dashboard and how to interpret them to assess overall project health

Updated today

Latest Update: 4-13-2026

The Project Dashboard provides a high-level view of schedule performance, risk, and execution trends. It helps project teams quickly understand where the project stands, identify emerging risks, and focus attention on areas that may require action

Project Dashboard Overview

The Project Dashboard is designed to answer three core questions:

  • Where does the project stand today?

  • How is the schedule performing against plan and baseline?

  • Where are the biggest risks or deviations emerging?

To do this, the dashboard combines schedule dates, critical path metrics, performance indices, quality checks, and progress visualizations.


Schedule and Time Metrics

These fields describe the current time boundaries and duration of the project.

Data Date

The Data Date represents the point in time up to which project progress has been recorded. For more information on the project data date, read this help article.

The Data Date is a critical reference for all performance and progress metrics shown on the dashboard.

  • All actuals (Actual Start / Actual Finish) are evaluated relative to the Data Date

  • Schedule calculations assume progress is accurate through this date


Performance and Progress Indices

These metrics evaluate how well the project is performing against plan and baseline.

Start Date

The Start Date reflects the start of the project based on the current schedule version.

Finish Date

The Finish Date reflects the projected completion date of the project based on current logic, durations, and progress.

Duration

The total number of calendar days between the project Start Date and Finish Date.

Critical Path Total Float

Critical Path Total Float represents the total amount of time activities on the critical path can be delayed without impacting the overall project finish date.

  • A value of zero or negative indicates no schedule flexibility

  • Negative float signals that the project is forecasted to finish late

% Complete

Displays overall project progress based on completed work.

  • Calculated from activity completion status

  • Provides a quick snapshot of execution progress


Activity State Overview

This section summarizes the execution state of activities across the project.

  • Completed — Finished activities

  • In Progress — Activities currently being worked

  • Not Started — Activities yet to begin

This view helps assess readiness and execution balance.

Progress State Overview

Activities are categorized by how they are performing relative to plan.

  • On Time — Progressing as planned

  • Early — Ahead of schedule, adding positive float

  • Late — Behind schedule and requiring attention


Critical Path and Float Metrics

These fields help identify schedule risk and flexibility.

Float Path 2 (Total Float)

Total float available on the second most critical path.

  • Indicates limited schedule flexibility beyond the primary critical path

  • Useful for identifying near-critical risks

Critical Path Length Index (CPLI)

CPLI measures how achievable the current project finish date is, based on remaining schedule flexibility.

Formula:

(Critical Path Length + Total Float) / Critical Path Length

Where:

  • Total Float is taken from the Finish Milestone

  • Critical Path Length is the sum of remaining durations on the critical path

How to interpret CPLI:

  • ≥ 1.00 Good: Project is on track or ahead

  • 0.95 – 0.99 Acceptable: Monitor closely

  • < 0.95 At Risk: Schedule intervention needed

Baseline Execution Index (BEI)

BEI measures how efficiently work is being completed relative to the original baseline plan.

Formula:

How to interpret BEI:

  • ≥ 1.00 — Excellent throughput

  • 0.95 – 0.99 — Moderate risk

  • < 0.95 — Warning: Falling behind baseline

BEI focuses on execution efficiency, not float or logic


Quality and Risk Indicators

These indicators highlight structural and execution-related risks

Schedule Quality Score (DCMA)

A composite score based on DCMA’s 14-Point Schedule Assessment

  • Higher scores indicate stronger scheduling practices

  • Highlights logic gaps, constraints, and structural issues

Note: For more information on how the quality score is calculated, read this article


Total Negative Float Activities Remaining

Number of remaining activities with negative total float

  • Indicates work that is already forecasted late


Total Remaining Critical Activities

Number of remaining activities on the critical path

  • A higher number may indicate concentrated risk


Progress S-Curve

The Progress S-Curve compares planned, actual, and projected progress over time

It helps answer:

  • Are we progressing as planned?

  • How far ahead or behind are we?

  • What happens if current trends continue?

S-Curve Reference Lines

  • Planned ES (Green)

    Planned progress assuming all activities start as early as possible

  • Planned LS (Red)

    Latest acceptable progress without delaying the project

  • Actual Progress (Solid Blue)

    What has actually been completed

  • Projected Progress (Dotted Blue)

    Forecasted progress based on current trends

A table below the curve shows variance from plan as a percentage:

  • Positive variance = ahead of baseline

  • Negative variance = behind baseline

Note: Toggle between Early Start and Late Start to see your variance from planned update


Planned Percentage Complete (PPC)

PPC compares what was planned to be completed versus what was actually completed.

Formula:

(Number of Completed Activities / Number of Planned Activities) × 100%

PPC can be viewed by:

  • Daily (small projects only)

  • Weekly

  • Monthly

And drilled down by:

  • Location

  • Responsibility (see below for example)

  • Custom codes (if configured)

PPC Color Indicators

PPC values are color-coded for quick interpretation:

  • < 75% (Red) High risk, well behind plan

  • 75% – 90% (Yellow) Caution, moderately behind

  • > 90% (Green) On track

PPC Bar Chart Rules

Each bar represents a time period and follows these rules:

  • If Planned = 0 and Completed = 0 → No value shown

  • If Completed < Planned → Percentage shown

  • If Completed > Planned → Capped at 100% with an indicator

Notes on Planned vs. Completed Activities

  • Completed Activities

    • Based on Actual Finish Date

    • Binned into the selected time period

  • Planned Activities

    • Based on Committed Finish Date

    • Taken from the Reference Version (typically baseline)

Only activities common to both versions are included in PPC calculations.


Variance Reason Details

Variance Reason Codes capture why activities did not proceed as planned.

Eligibility

Variance reasons can be assigned only to activities that are:

  • In Progress

  • Completed

Timeframes

Variance reasons can be analyzed:

  • Daily

  • Weekly

  • Monthly

Visualization Options

Stacked Bar Chart

Shows distribution of variance reasons over time.

  • View by Percentage (%) or Count (#)

  • Helps identify trends or spikes in specific issues

Donut Chart

Provides a high-level breakdown of variance reasons for a selected timeframe.

  • Includes a table with raw counts

  • Useful for reporting and root cause analysis


Watchlist

Displays all activities, milestones, or elements that have been manually added to the Watchlist.

  • Helps track high-risk or high-priority items



Related Help Articles

Did this answer your question?